Public–private partnership

From Wikipedia, the free encyclopedia
Jump to navigation Jump to search
Depiction of the various levels of private-sector involvement in public private partnerships. Source: Brookings Institution

A public–private partnership (PPP, 3P or P3) is a cooperative arrangement between two or more public and private sectors, typically of a long-term nature.[1][2] They are primarily used for infrastructure provision, such as the building and equipping of schools, hospitals, transport systems, water and sewerage systems.[3] PPPs have been highly controversial as funding tools, largely over concerns that public return on investment is lower than returns for the private funder. It is closely related to concepts such as privatization and the contracting out of government services.[1][4] The lack of a shared understanding of what a PPP is makes the process of evaluating whether PPPs have been successful complex.[5] Evidence of PPP performance in terms of VfM and efficiency, for example, is mixed and often unavailable.[5] Common themes of PPPs are the sharing of risk and the development of innovation.[5]

Definition[edit]

There is no consensus about how to define a PPP.[4] The PPP phrase can cover hundreds of different types of long term contracts with a wide range of risk allocations, funding arrangements and transparency requirements.[1] The advancement of PPPs, as a concept and a practice, is a product of the new public management of the late 20th century and globalization pressures. The term "public-private partnership" is prey to thinking in parts rather than the whole of the partnership, which makes it difficult to pin down a universally accepted definition of PPPs.[citation needed]

The Government of India defines a P3 as "a partnership between a public sector entity (sponsoring authority) and a private sector entity (a legal entity in which 51% or more of equity is with the private partner/s) for the creation and/or management of infrastructure for public purpose for a specified period of time (concession period) on commercial terms and in which the private partner has been procured through a transparent and open procurement system."[6] According to Weimer and Vining, "A P3 typically involves a private entity financing, constructing, or managing a project in return for a promised stream of payments directly from government or indirectly from users over the projected life of the project or some other specified period of time".[7]

A 2013 study published in State and Local Government Review found that definitions of public-private partnerships vary widely between municipalities: "Many public and private officials tout public-private partnerships for any number of activities, when in truth the relationship is contractual, a franchise, or the load shedding of some previously public service to a private or nonprofit entity." A more general term for such agreements is "shared service delivery" — municipalities joining together, with private firms, or with nonprofits to provide services to citizens.[8][9]

Origins[edit]

Governments have used such a mix of public and private endeavors throughout history.[10][11] Muhammad Ali of Egypt utilized "concessions" in the early 1800s to obtain public works for minimal cost while the concessionaires' companies made most of the profits from projects such as railroads and dams.[12] Much of the early infrastructure of the United States was built by what can be considered public-private partnerships. This includes an early steamboat line between New York and New Jersey in 1808, many of the railroads including the nation's first railroad chartered in New Jersey in 1815, and most of the modern electric grid.[citation needed] In Newfoundland Robert Gillespie Reid contracted to operate the railways for fifty years from 1898, though originally they were to become his property at the end of the period.[citation needed] However, the late 20th century and early 21st century[when?] saw a clear trend towards governments across the globe making greater use of various PPP arrangements.[2] This trend seems to have reversed since the global financial crisis of 2008.[5]

Pressure to change the standard model of public procurement arose initially from concerns about the level public debt, which grew rapidly during the macroeconomic dislocation of the 1970s and 1980s. Governments sought to encourage private investment in infrastructure, initially on the basis of accounting fallacies arising from the fact that public accounts did not distinguish between recurrent and capital expenditures.[citation needed] In Japan since the 1980s, the third sector (第三セクター, daisan sekutā) refers to joint corporations invested in by both public and private sectors.[citation needed]

In 1992, the Conservative government of John Major in the UK introduced the PFI,[13] the first systematic programme aimed at encouraging public-private partnerships. The 1992 programme focused on reducing the public sector borrowing requirement, although, as already noted, the effect on public accounts was largely illusory. The Labour government of Tony Blair, elected in 1997, expanded the PFI initiative but sought to shift the emphasis to the achievement of "value for money", mainly through an appropriate allocation of risk. However, it has since been found that many programs ran dramatically over budget and have not presented as value for money for the taxpayer, with some projects costing more to cancel than to complete. An in-depth study, conducted by the National Audit Office of the United Kingdom [14] concluded that the private finance initiative model had proved to be more expensive and less efficient in providing hospitals, schools and other public infrastructure than public financing.

Economic theory[edit]

In economic theory, public–private partnerships have been studied through the lens of contract theory. The first theoretical study on PPPs was conducted by Oliver Hart.[15] From an economic theory perspective, what distinguishes a PPP from traditional public procurement of infrastructure services is the fact that in the case of PPPs the building and operating stages are bundled. Hence, the private firm has strong incentives in the building stage to make investments with regard to the operating stage. These investments can be desirable but may also be undesirable (e.g., when the investments not only reduce operating costs, but also reduce service quality). Hence, there is a trade-off and it depends on the particular situation whether a PPP or traditional procurement is to be preferred. Hart's model has been extended in several directions. For instance, authors have studied various externalities between the building and operating stages,[16] insurance when firms are risk-averse,[17] and implications of PPPs for incentives to innovate and gather information.[18]

Clarence N. Stone frames the public private partnership as 'governing coalitions'. In Regime Politics Governing Atlanta 1946–1988, he specifically analyzes the 'crosscurrents in coalition mobilization'. Government coalitions are revealed as susceptible to a number of problems primarily corruption and conflicts of interests. This slippery slope is generally created by a lack of sufficient oversight.[19] Corruption and conflicts of interests, in this case, leads to costs of opportunism; other costs related to P3's are production and bargaining costs.[20]

Funding Models[edit]

In some types of PPP, the cost of using the service is borne exclusively by the users of the service - for example, hospital patients, students or users of public utilities.[2]In other types (notably the PFI), capital investment is made by the private sector on the basis of a contract with government to provide agreed services and the cost of providing the service is borne wholly or in part by the government. Government contributions to a PPP may also be in kind (notably the transfer of existing assets). In projects that are aimed at creating public goods like in the infrastructure sector, the government may provide a capital subsidy in the form of a one-time grant, so as to make the project economically viable. In some other cases, the government may support the project by providing revenue subsidies, including tax breaks or by guaranteed annual revenues for a fixed time period. In all cases, the partnerships include a transfer of significant risks to the private sector, generally in an integrated and holistic way, minimizing interfaces for the public entity.[citation needed] Case-by-case project governance and funding and financing interventions are the main value generators for delivering public service[21][22]. Because P3s are directly responsible for a variety of activities P3s can evolve into monopolies motivated by rent-seeking behavior(s).[7]

Typically, a private sector consortium forms a special company called a "special purpose vehicle" (SPV) to develop, build, maintain and operate the asset for the contracted period.[23][24] In cases where the government has invested in the project, it is typically (but not always) allotted an equity share in the SPV.[25] The consortium is usually made up of a building contractor, a maintenance company and equity investor(s). It is the SPV that signs the contract with the government and with subcontractors to build the facility and then maintain it. In the infrastructure sector, complex arrangements and contracts that guarantee and secure the cash flows make PPP projects prime candidates for project financing. A typical PPP example would be a hospital building financed and constructed by a private developer and then leased to the hospital authority. The private developer then acts as landlord, providing housekeeping and other non-medical services while the hospital itself provides medical services.[23]

There are many drivers for PPPs[2][26]. One common driver involves the claim that PPPs enable the public sector to harness the expertise and efficiencies that the private sector can bring to the delivery of certain facilities and services traditionally procured and delivered by the public sector.[27] Another common driver is that PPPs may be structured so that the public sector body seeking to make a capital investment does not incur any borrowing. Rather, the PPP borrowing is incurred by the private sector vehicle implementing the project. On PPP projects where the cost of using the service is intended to be borne exclusively by the end user, the PPP is, from the public sector's perspective, an "off-balance sheet" method of financing the delivery of new or refurbished public sector assets. On PPP projects where the public sector intends to compensate the private sector through availability payments once the facility is established or renewed, the financing is, from the public sector's perspective, "on-balance sheet"; however, the public sector will regularly benefit from significantly deferred cash flows.[citation needed] This viewpoint has been contested through research that shows that a majority of PPP projects ultimately cost significantly more than traditional public ones.[28][29] Generally, financing costs will be higher for a PPP than for traditional public financing, because of the private sector higher cost of capital. However, extra financing costs can be offset by private sector efficiency, savings resulting from a holistic approach to delivering the project or service, and from the better risk allocation in the long run.[citation needed]

Profit-sharing[edit]

Some public-private partnerships, when the development of new technologies is involved, include profit sharing agreements. This generally involves splitting revenues between the inventor and the public once a technology is commercialized. Profit sharing agreements can stand over a fixed period of time, or in perpetuity.[30]

Long term infrastructure contracts[edit]

Infrastructure PPPs as a phenomenon can be understood at five different levels: as a particular project or activity, as a form of project delivery, as a statement of government policy, as a tool of government, or as a wider cultural phenomenon.[5] Different disciplines commonly emphasize different aspects of the PPP phenomena.[5] The engineering and economics professions primarily take a utilitarian, functional focus emphasising concerns such as project delivery and relative value-for-money (VfM) compared to the traditional ways of delivering large infrastructure projects. In contrast, public administrators and political scientists tend to view PPPs more as a policy brand, and as a useful tool for governments to achieve their objectives.[citation needed]

Growth and decline[edit]

From 1990 to 2009 nearly 1,400 PPP deals were signed in the European Union, representing a capital value of approximately €260 billion.[31] Since the onset of the financial crisis in 2008, estimates suggest that the number of PPP deals closed has fallen more than 40 percent.[32][33]

Investments in public sector infrastructure are seen as an important means of maintaining economic activity, as was highlighted in a European Commission communication on PPPs.[34] As a result of the significant role that PPPs have adopted in the development of public sector infrastructure, in addition to the complexity of such transactions, the European PPP Expertise Centre (EPEC) was established to support public-sector capacity to implement PPPs and share timely solutions to problems common across Europe in PPPs.[35]

U.S. city managers' motivations for exploring public–private service delivery vary. According to a 2007 survey, two primary reasons were expressed: cost reduction (86.7%) and external fiscal pressures, including tax restrictions (50.3%). No other motivations expressed exceeded 16%. In the 2012 survey, however, interest had shifted to the need for better processes (69%), relationship building (77%), better outcomes (81%), leveraging resources (84%), and belief that collaborative service delivery is "the right thing to do" (86%). Among those surveyed, the provision of public services through contracts with private firms peaked in 1977 at 18% and has declined since. The most common form of shared service delivery now involves contracts between governments, growing from 17% in 2002 to 20% in 2007. "At the same time, approximately 22% of the local governments in the survey indicated that they had brought back in-house at least one service that they had previously provided through some alternative private arrangement."[8]

Effectiveness[edit]

The effectiveness of PPPs as cost-saving or innovation-producing ventures has been called into question by numerous studies. A common problem with PPP projects is that private investors obtained a rate of return that was higher than the government's bond rate, even though most or all of the income risk associated with the project was borne by the public sector.[33] A UK Parliament report [36]underlines that some private investors have made large returns from PPP deals, suggesting that departments are overpaying for transferring the risks of projects to the private sector, one of the Treasury’s stated benefits of PPP.

A 2008 report by PriceWaterhouseCoopers argued that the comparison between public and private borrowing rates is not fair, because there are "constraints on public borrowing", which may imply that public borrowing is too high, and so PFI projects can be beneficial by not putting debt directly on government books.[37] The fact that PPPs debt is not recorded as debt and remains largely "off balance sheet" has become a major concern. Indeed, keeping the PPP project and its contingent liabilities ‘off balance sheet,’ means that the true cost of the project is hidden[38]. According to the International Monetary Fund, economic ownership of the asset should determine whether to record PPP-related assets and liabilities in the government’s or the private corporation’s balance sheet is not straightforward[39]. According to a 2018 UN Report [29], "in terms of costs, private finance is more expensive than public finance, and public-private partnerships can also incur high design, management and transactional costs due to their complexity and the need for external advice [40]. In addition, negotiations on issues other than traditional procurement can cause project delays of some years [41].

Contract management is a crucial factor in shared service delivery[42], and services that are more challenging to monitor or fully capture in contractual language often remain in municipal control. In the 2007 survey of U.S. city managers, the most difficult was judged to be the operation and management of hospitals, and the least difficult the cleaning of streets and parking lots. The study revealed that communities often fail to sufficiently monitor collaborative agreements or other forms of service delivery: "For instance, in 2002, only 47.3% of managers involved with private firms as delivery partners reported that they evaluate that service delivery. By 2007, that was down to 45.4%. Performance monitoring is a general concern from these surveys and in the scholarly criticisms of these arrangements."[8][9]

In Ontario, a 2012 review of 28 projects showed that the costs were on average 16% lower for traditional publicly procured projects, rather than PPPs.[28] A number of Australian studies of early initiatives to promote private investment in infrastructure concluded that, in most cases, the schemes being proposed were inferior to the standard model of public procurement based on competitively tendered construction of publicly owned assets.[43] In 2009, the New Zealand Treasury, in response to inquiries by the new National Party government, released a report on PPP schemes that concluded that "there is little reliable empirical evidence about the costs and benefits of PPPs" and that there "are other ways of obtaining private sector finance", as well as that "the advantages of PPPs must be weighed against the contractual complexities and rigidities they entail".[44]

One response to these negative findings was the development of formal procedures for the assessment of PPPs in which the focus was on "value for money" (VfM) rather than reductions in debt. The underlying framework was one in which value for money is achieved by an appropriate allocation of risk. These assessment procedures were incorporated in the private finance initiative and its Australian counterparts from the late 1990s onwards.[citation needed] A 2012 study showed that VfM frameworks were still inadequate to provide an effective method of evaluating PPP proposals.[28]

Another model being discussed is the public-private-community partnership (PPCP), in which both the government and private players work together for social welfare, eliminating the prime focus of private players on profit.[citation needed] This model is being applied more in developing nations such as India.[citation needed]

Privatisation of water[edit]

After a wave of privatisation of many water services in the 1990s, mostly in developing countries, experiences show that global water corporations have not brought the promised improvements in public water utilities. Instead of lower prices, large volumes of investment and improvements in the connection of the poor to water and sanitation, water tariffs have increased out of reach of poor households. Water multinationals are withdrawing from developing countries and the World Bank is reluctant to provide support.[45]

The privatisation of the water services of the city of Paris was proven to be unwanted and at the end of 2009 the city did not renew its contract with two of the French water corporations, Suez and Veolia.[46][47] After one year of being controlled by the public, it is projected that the water tariff will be cut by between 5% and 10%.[48]

Health services[edit]

For more than two decades public-private partnerships have been used to finance health infrastructure. Governments may look to the PPP-model to solve larger problems in healthcare delivery. While the provision of health is widely recognized as the responsibility of government, private capital and expertise can be viewed as sources to induce efficiency and innovation.[opinion] However, some healthcare-related PPP's have been shown to cost significantly more money to develop and maintain than those developed through traditional public procurement.[49]

A health services PPP can be described as a long-term contract (typically 15–30 years) between a public-sector authority and one or more private sector companies operating as a legal entity. The government provides purchasing power, outlines goals for an optimal health system, and contracts private enterprise to innovate, build, maintain and/or manage the delivery of agreed-upon services over the term of the contract. The private sector receives payment for its services and assumes substantial financial, technical and operational risk while benefitting from the upside potential of shared cost savings.[citation needed]

The private entity is made up of any combination of participants who have a vested interested in working together to provide core competencies in operations, technology, funding and technical expertise. The opportunity for multi-sector market participants includes hospital providers and physician groups, technology companies, pharmaceutical and medical device companies, private health insurers, facilities managers and construction firms. Funding sources could include banks, private equity firms, philanthropists and pension fund managers.[citation needed]

The larger scope of health PPPs to manage and finance care delivery and infrastructure means a larger potential market for private organizations. Health spending in the United States accounts for approximately half of all health spending among OECD nations, but the biggest growth will be outside of the U.S. In 2010, PricewaterhouseCoopers projected that spending on healthcare among the Organisation for Economic Co-operation and Development (OECD) and BRIC nations of Brazil, Russia, India and China would grow by 51 per cent between 2010 and 2020, with China and India expected to increase the most. This amounts to a cumulative total of more than $71 trillion.[50] Of this, $3.6 trillion is projected to be spent on health infrastructure and $68.1 trillion will be spent on non-infrastructure health spending cumulatively over the next decade. Annually, spending on health infrastructure among the OECD and BRIC nations is projected to increase to $397 billion by 2020, up from $263 billion in 2010. The larger market for health PPPs is projected to be in non-infrastructure spending, estimated to be more than $7.5 trillion annually, up from $5 trillion in 2010.[50]

Product development partnerships[edit]

Product development partnerships (PDPs) are a class of public–private partnerships that focus on pharmaceutical product development for diseases of the developing world. These include preventive medicines such as vaccines and microbicides, as well as treatments for otherwise neglected diseases. PDPs were first created in the 1990s to unite the public sector's commitment to international public goods for health with industry's intellectual property, expertise in product development, and marketing.[citation needed]

International PDPs work to accelerate research and development of pharmaceutical products for underserved populations that are not profitable for private companies. They may also be involved in helping plan for access and availability of the products they develop to those in need in their target populations. Publicly financed, with intellectual property rights granted by pharmaceutical industry partners for specific markets, PDPs have less concern over recouping development costs through the profitability of the products being developed.[opinion] These not-for-profit organizations combine public- and private-sector interests, with a view toward resolving the specific incentive and financial barriers to increased industry involvement in the development of safe and effective pharmaceutical products.[citation needed]

Some of the work of the World Health Organization (WHO) may be considered global public–private partnerships (GPPPs).[opinion] The WHO is financed through the UN system by contributions from member states. In recent years, WHO's work has involved more collaboration with NGOs and the pharmaceutical industry, as well as with foundations such as the Bill and Melinda Gates Foundation and the Rockefeller Foundation. 15% of WHO's total revenue in 2012 was financed by private foundations.[51]

Centralised units[edit]

The World Bank (2007)[52] states that governments tend to create Centralised PPP Units as a response to weaknesses in the central government's ability to effectively manage PPP programmes. Different governments suffer from different institutional failures in the PPP procurement process, hence these Centralised PPP units need to address these different issues by shaping their functions to suit the individual government needs. The function, location (within government) and jurisdiction (i.e. who controls it) of dedicated PPP Units may differ amongst countries, but generally, these include:

  • Policy guidance and advice on the content of national legislation. The guidance also includes defining which sectors are eligible for PPPs as well as which PPP methods and schemes can be carried out.
  • Approving or rejecting proposed PPP projects i.e. playing a gatekeeper role that can occur at any stage of the process i.e. at the initial planning stage or at the final approval stage.
  • Providing technical support to government organisations at the project identification, evaluation, procurement or contract management phase.
  • Capacity building i.e. training of public sector officials that are involved in PPP programmes or are interested in the PPP process.
  • Promote PPPs within the private sector i.e. PPP market development.

A 2013 review[53] which targeted research based on the value of centralised PPP Units (and does not look at the value of PPPs in general or any other type of PPP arrangement as the review was aimed at providing evidence needed to decide whether or not to set up a Centralised PPP Unit) found-

  • No quantitative evidence: There is very little quantitative evidence of the value of centralised PPP coordination units against ministries or government agencies individually procuring PPP projects. Most of the studies available on PPP Units tend to focus on their role and only carry out brief descriptive analyses of their value.
  • Limited Authority: The majority of the PPP Units reviewed in the literature do not play a particularly important role in approving or rejecting PPP programmes or projects. Whilst their advice is used in the decision-making process by other government bodies, the majority do not actually have any executive power to make such decisions themselves. Hence, when they have more authority their value is seen to be higher.
  • PPP Units differ by country and sector: Government failures, in regards to PPP units, vary by government. The requirements for PPPs also vary by country and sector and so do the risks involved (i.e. financial, social etc.) for the country government. Hence, PPP Units need to be tailored to solve these failures, properly assess risks and be located in the correct government departments where it can command the most power. PPP Units can play a number of important roles in the PPP process; however, not all PPP Units will play the same role as their functions have been tailored to individual country needs. In some cases, limits to their authority have curtailed their effectiveness.
  • Implicit value: The lack of rigorous evidence does not prove that PPP Units are not an important contributor to the success of a country's PPP programme. The literature review does show that whilst there is no quantitative data, there are widespread perceptions on the importance of a well-functioning PPP unit for the success of a country's PPP programme.

The author of the 2013 review[53] found no literature that rigorously evaluates the usefulness of PPP Units. The literature does show that PPP Units should be individually tailored to different government functions, address different government failures and be appropriately positioned to support the country's PPP Programme. Where these conditions seem to have been met, there is a consensus that PPP Units have played a positive role in national PPP Programmes.

Partnerships with non-profit organizations[edit]

Public-private partnerships with non-profits and private partners have seen a large increase over the years in part because local and state governments rely heavily on the growing number of non-profits to provide many public services.[54] Neighbourhood organizations or small and local non-profits saw a broad source of funding during the early years but there has been a shift in funding more recently reducing the overall funding and seeing more of it go to larger agencies focusing on large grants.[citation needed]

With the rise in public–private partnerships there is also a rise in the responsibility that the non-profits tend to hold. With some governments relying on many more of these organizations to provide public services it is also proving difficult for the government to hold these non-profits responsible.[54] Too many projects and partnerships can also lead to a lack of accountability.[55] A lack of defined accountability roles can also lead to some taking advantage of others, causing a distrustful partnership.[56] Many partnerships can be terminated early due to issues with trust and cooperation during the contract implementation process. These issues can be avoided when the organization has initial guidelines for dos and don'ts,[57] and a continuous commitment to negotiations in any time of trouble and even an outline for termination procedures if necessary.[55]

When entering into a cross-sector partnership, problems may arise due to differences in the culture of government, industry and non-profits. Items like performance measures, goal measurements, government regulations, and the nature of funding can all be interpreted differently thus causing blurred lines of communication.[55] Conflicts can also be related to territorialism or protectionism, and a lack of commitment to working within the partnership.[58] A business partnership model would not be accurate or appropriate for a P3.[57]


See also[edit]

References[edit]

  1. ^ a b c Hodge, G. A and Greve, C. (2007), Public–Private Partnerships: An International Performance Review, Public Administration Review, 2007, Vol. 67(3), pp. 545–558
  2. ^ a b c d Roehrich, Jens K.; Lewis, Michael A.; George, Gerard (2014). "Are public–private partnerships a healthy f? A systematic literature review". Social Science & Medicine. 113: 110–119. doi:10.1016/j.socscimed.2014.03.037. PMID 24861412.
  3. ^ Bovaird, Tony (2015-09-25). Public Management and Governance. doi:10.4324/9781315693279. ISBN 9781315693279.
  4. ^ a b Marta Marsilio, M., Cappellaro, G and Cuccurullo, C. (2011), The Intellectual Structure Of Research Into PPPs, Public Management Review, Vol 13 (6), pp.763–782
  5. ^ a b c d e f Hodge, G.A. and Greve, C. (2016), On Public-Private Partnership Performance: A Contemporary Review, Public Works Management & Policy, pp. 1–24
  6. ^ "PPP". Department of Economic Affairs, Ministry of Finance, Government of India. 2007. Archived from the original on 2012-06-16.
  7. ^ a b Policy Analysis Edition No.05. Pearson, Inc. 2011. p. 309. ISBN 978-0-205-78130-0.
  8. ^ a b c Hilvert, Cheryl; Swindell, David (2014). "Collaborative Service Delivery: What Every Local Government Manager Should Know". State and Local Government Review. 45.
  9. ^ a b "Local government services and contracts: Best practices and key issues to watch". JournalistsResource.org, retrieved February 14, 2014
  10. ^ Wettenhall, R. (2019), The Public–Private Interface: Surveying the History, in G. Hodge and C. Greve (eds.), The Challenge of Public–Privapppte Partnerships: Learning from International Experience, Cheltenham UK: Edward Elgar
  11. ^ Wettenhall, R. (2000), Mixes and partnerships through time, in G.A. Hodge, C. Greve and A. Boardman (eds.),International Handbook in Public–Private Partnerships, Cheltenham UK: Edward Elgar
  12. ^ Karabell, Zachary (2003). Parting the desert: the creation of the Suez Canal. Alfred A. Knopf. p. 34. ISBN 978-0-375-40883-0.
  13. ^ Allen, Grahame. "The Private Finance Initiative (PFI) Commons Briefing papers RP01-117" (PDF). UK Parliament: House of Commons Library. UK Government. Retrieved 20 January 2018.
  14. ^ See United Kingdom, National Audit Office, PF1 and PF2, a report by the Comptroller and Auditor General (London, 2018)
  15. ^ Hart, Oliver (2003). "Incomplete Contracts and Public Ownership: Remarks, and an Application to Public–Private Partnerships*". The Economic Journal. 113 (486): C69–C76. doi:10.1111/1468-0297.00119. ISSN 1468-0297.
  16. ^ Bennett, John; Iossa, Elisabetta (2006). "Building and managing facilities for public services". Journal of Public Economics. 90 (10–11): 2143–2160. CiteSeerX 10.1.1.499.505. doi:10.1016/j.jpubeco.2006.04.001.
  17. ^ Iossa, Elisabetta; Martimort, David (2012). "Risk allocation and the costs and benefits of public–private partnerships". The RAND Journal of Economics. 43 (3): 442–474. CiteSeerX 10.1.1.639.9312. doi:10.1111/j.1756-2171.2012.00181.x. ISSN 1756-2171.
  18. ^ Hoppe, Eva I.; Schmitz, Patrick W. (2013). "Public–private partnerships versus traditional procurement: Innovation incentives and information gathering" (PDF). The RAND Journal of Economics. 44 (1): 56–74. doi:10.1111/1756-2171.12010. ISSN 1756-2171.
  19. ^ Stone, Clarence N. (1989). Regime Politics Governing Atlanta, 1946–1988. 0-7006-0415-4: University Press of Kansas. pp. 148–149.
  20. ^ Policy Analysis Edition No.05. Pearson, Inc. 2011. pp. 311–315. ISBN 978-0-205-78130-0.
  21. ^ Cardenas, I.; Voordijk, H; Geert, D. (2017). "Beyond theory: Towards a probabilistic causation model to support project governance in infrastructure projects". International Journal of Project Management. 35 (3): 432–450. doi:10.1016/j.ijproman.2017.01.002.
  22. ^ Cardenas, I.; Voordijk, H; Geert, D. (2018). "Beyond project governance. Enhancing funding and enabling financing for infrastructure in transport. Findings from the importance analysis approach". European Journal of Transport and Infrastructure Research. 18 (4). doi:10.18757/ejtir.2018.18.4.3261.
  23. ^ a b Barlow, J.; Roehrich, J.K.; Wright, S. (2013). "Europe Sees Mixed Results From Public-Private Partnerships For Building And Managing Health Care Facilities And Services". Health Affairs. 32 (1): 146–154. doi:10.1377/hlthaff.2011.1223. PMID 23297282.
  24. ^ Zheng, J.; Roehrich, J.K.; Lewis, M.A. (2008). "The dynamics of contractual and relational governance: Evidence from long-term public–private procurement arrangements". Journal of Purchasing and Supply Management. 14 (1): 43–54. doi:10.1016/j.pursup.2008.01.004.
  25. ^ Moszoro M., Gasiorowski P. (2008), 'Optimal Capital Structure of Public–Private Partnerships', IMF Working Paper 1/2008. Papers.ssrn.com (2008-01-25). Retrieved on 2011-11-20.
  26. ^ http://www.unesco-mars.com/pdf_document/Peccia_et_al._Public_private_partnership_VIII_1_2017_1.pdf
  27. ^ Caldwell, Nigel D.; Roehrich, Jens K.; George, Gerard (September 2017). "Social Value Creation and Relational Coordination in Public-Private Collaborations". Journal of Management Studies. 54 (6): 906–928. doi:10.1111/joms.12268.
  28. ^ a b c Siemiatycki, Matti; Farooqi, Naeem (July 2012). "Value for Money and Risk in Public-Private Partnerships". Journal of the American Planning Association. 78 (3): 286–299. doi:10.1080/01944363.2012.715525.
  29. ^ a b Extreme poverty and human rights*, Report of the Special Rapporteur on extreme poverty and human rights, Philip Alston,submitted in accordance with Human Rights Council resolution 35/19, NYC, 26 September 2019
  30. ^ Vincent, Donovan (1 July 2019). "Who should share in the risks and rewards of Sidewalk Labs' smart city on Toronto's waterfront? | The Star". thestar.com. Toronto Star. Retrieved 1 July 2019.
  31. ^ Public Private Partnerships in Europe. Archived 2010-08-08 at the Wayback Machine. (PDF) . Retrieved on 2011-11-20.
  32. ^ PFI projects hit fresh low as few deals closed. Ft.com (2010-01-13). Retrieved on 2011-11-20.
  33. ^ a b Barlow, J. Roehrich; Wright, S. (2010). "De facto privatisation or a renewed role for the EU? Paying for Europe's healthcare infrastructure in a recession". Journal of the Royal Society of Medicine. 103 (2): 51–55. doi:10.1258/jrsm.2009.090296. PMC 2813788. PMID 20118334.
  34. ^ European Commission Communication on PPP November 2009[dead link]
  35. ^ European PPP Expertise Centre. Eib.org. Retrieved on 2011-11-20.
  36. ^ "Treasury must set out clear position on PFI - News from Parliament". UK Parliament. Retrieved 2018-06-27.
  37. ^ Public Sector Research Center. "The Value of PFI: Hanging in the balance (sheet)?". PriceWaterhouseCoopers. p. 22. Missing or empty |url= (help)
  38. ^ Romero, Maria Jose (2015). What lies beneath? A critical assessment of PPPs and their impact on sustainable development. http://www.eurodad.org/files/pdf/1546450-what-lies-beneath-a-critical-assessment-of-ppps-and-their-impact-on-sustainable-development-1450105297.pdf: Eurodad. p. 5.
  39. ^ GOVERNMENT FINANCE STATISTICS MANUAL 2014. Washington: IMF. 2014. pp. 324–327. ISBN 978-1-49834-376-3.
  40. ^ See Languille, “Public-private partnerships in education and health in the global South”, p. 156; and Germà Bel and Xavier Fageda, “What have we learned from the last three decades of empirical studies on factors driving local privatization? ”, Local Government Studies, vol. 43, No. 4 (2017), pp. 503–511
  41. ^ See European Court of Auditors, Public-Private Partnerships in the EU, p. 9
  42. ^ Cardenas, I.; Voordijk, H; Geert, D. (2017). "Beyond theory: Towards a probabilistic causation model to support project governance in infrastructure projects". International Journal of Project Management. 35 (3): 432–450. doi:10.1016/j.ijproman.2017.01.002.
  43. ^ Economic Planning Advisory Commission (EPAC) 1995a,b; House of Representatives Standing Committee on Communications Transport and Microeconomic Reform 1997; Harris 1996; Industry Commission 1996; Quiggin 1996
  44. ^ "Brian Rudman: Promised electric trains derailed by misguided enthusiasm". The New Zealand Herald. 1 June 2009. Retrieved 21 February 2010.
  45. ^ the Water Justice Project on Transnational Institute
  46. ^ Reversal of privatisation of Paris' water. Cupe.ca (2010-02-25). Retrieved on 2011-11-20.
  47. ^ Deputy Mayor of Paris Anne Le Strat tells how Paris put water services back into public hands. Canadians.org (2011-02-18). Retrieved on 2011-11-20.
  48. ^ Water tariff cut. Globalwaterintel.com (2011-01-13). Retrieved on 2011-11-20.
  49. ^ Reynolds, Keith (3 August 2017). "The enormous cost of public-private partnerships". Policy Note. Retrieved 28 June 2019.
  50. ^ a b PricewaterhouseCoopers' Health Research Institute, (2010). [Build and Beyond: The (r)evolution of healthcare PPPs] http://www.pwc.com/us/ppphealth, p9.
  51. ^ Sixty – sixth world assembly, WHO
  52. ^ World Bank (2007) "Public-Private Partnership Units: Lessons for their designs and use in infrastructure"
  53. ^ a b Alberto Lemma. "Literature Review: Evaluating the Costs and Benefits of Centralised PPP Units". EPS PEAKS.
  54. ^ a b Smith, S. (2008). "The Challenge of Strengthening Nonprofits and Civil Society". Public Administration Review. 68 (supplement s1): 132–145. doi:10.1111/j.1540-6210.2008.00984.x.
  55. ^ a b c Babiak, K. & Thibault, L. (2009). "Challenges in Multiple Cross-Sector Partnerships". Nonprofit and Voluntary Sector Quarterly. 38 (1): 117–143. doi:10.1177/0899764008316054.
  56. ^ Eschenfelder, B. (2011). "Funder-Initiated Integration Partnership Challenges and Strategies". Nonprofit Management and Leadership. 21 (3): 273–288. doi:10.1002/nml.20025.
  57. ^ a b Bloomfield, P. (2006). "The Challenging Business of Long-Term Public–Private Partnerships: Reflections on Local Experience". Public Administration Review. 66 (3): 400–411. doi:10.1111/j.1540-6210.2006.00597.x.
  58. ^ Cairns, B. & Harris, M. (2011). "Local cross-sector partnerships" (PDF). Nonprofit Management and Leadership. 21 (3): 311–324. doi:10.1002/nml.20027.

[1]

Further reading[edit]

  • Abou-bakr, A (2013), Managing Disasters Through Public–Private Partnerships,Georgetown University Press.
  • Burnett, M. "PPP – A decision maker's guide", European Institute of Public Administration, 2007
  • Chinchilla, C. "El nuevo contrato de colaboración entre el setor público y el sector privado", Revista Española de Derecho Administrativo nº 132 (2006)
  • Delmon, J. "Private Sector Investment in Infrastructure: Project finance, PPP projects and risk," Kluwer, 2009.
  • Delmon, J. "Public Private Partnership Programs: Creating a framework for private sector investment in infrastructure, Kluwer, 2014.
  • Gonzalez Garcia, J. "El contrato de colaboración público privada", Revista de Administración Pública, nº 170 (2006).
  • Koh, Jae Myong (2018) Green Infrastructure Financing: Institutional Investors, PPPs and Bankable Projects, Palgrave Macmillan. ISBN 978-3-319-71769-2.
  • Linotte Didier, Un cadre juridique désormais sécurisé pour les contrats de partenariat, AJDA, n° 1/2005 du 10 janvier 2005.
  • Monera Frédéric, Les financements innovants de services et de projets publics, Revue de la Recherche Juridique – Droit prospectif, PUAM, 2005-1, p. 337 & s.
  • Moszoro M., Gasiorowski P. (2008), 'Optimal Capital Structure of Public–Private Partnerships', IMF Working Paper 1/2008. [1]
  • Colman, J. (2002), 'Mumbo jumbo…and other pitfalls:Evaluating PFI/PPP projects', National Audit Office PFI / PPP Conference "Bringing about beneficial change, London, May.
  • Economic Planning Advisory Commission (EPAC) (1995), 'Final Report of the Private Infrastructure Task Force', Australian Government Publishing Service, Canberra.
  • Economic Planning Advisory Commission (EPAC) (1995), 'Interim Report of the Private Infrastructure Task Force', Australian Government Publishing Service, Canberra.
  • Harris, A.C. (1996), 'Financing infrastructure: private profits from public losses', Audit Office of NSW, Public Accounts Committee, Parliament of NSW, Conference, Public/Private infrastructure financing: Still feasible?, Sydney, September.
  • Hart, Oliver (2003). "Incomplete contracts and public ownership: Remarks, and an application to public‐private partnerships". Economic Journal 113: C69-C76.
  • Hoppe, Eva I.; Schmitz, Patrick W. (2013). "Public‐private partnerships versus traditional procurement: Innovation incentives and information gathering" (PDF). RAND Journal of Economics. 44: 56–74. doi:10.1111/1756-2171.12010.
  • House of Representatives Standing Committee on Communications Transport and Microeconomic Reform, (1997), 'Planning not Patching: An Inquiry Into Federal Road Funding', The Parliament of the Commonwealth of Australia, Australian Government Publishing Service, Canberra.
  • Industry Commission (1996), 'Competitive Tendering and Contracting by Public Sector Agencies', Australian Government Publishing Service, Canberra.
  • Iossa, Elisabetta and Martimort, David (2012). "Risk allocation and the costs and benefits of public‐private partnerships". RAND Journal of Economics 43: 442–474.
  • Minnow, Martha and Jody Freeman (2009), Government By Contract: Outsourcing and American Democracy, Harvard U.P.
  • Möric, K. (2009), 'Les partenariats public-privé – le choix du partenaire privé au regard du droit communautaire, Editions Larcier, 264 p.
  • Onses, Richard (2003). The Public Private Partnership of Cartagena de Indias – Colombia: Agbar's Experience. Barcelona. ISBN 978-84-607-8089-2.
  • Quiggin, J. (1996), 'Private sector involvement in infrastructure projects', Australian Economic Review, 1st quarter, 51–64.
  • Schaeffer, PV and S Loveridge (2002), 'Toward an Understanding of Types of Public-Private Cooperation'. Public Performance and Management Review 26(2): 169–189.
  • Spackman, M. (2002), 'Public-private partnerships: lessons from the British approach', Economic Systems, 26(3), 283–301.
  • Strauch, L. (2009), 'Public Private Partnership in European Road Infrastructure: PPP as Investment Asset Following the M6 Road Project in Hungary', VDM.
  • Nazar Talibdjanov and Sardorbek Koshnazarov, UNDP & Chamber of Commerce and Industry of Uzbekistan, Public-Private Partnership in Uzbekistan: Problems, Opportunities and Ways of Introduction (2008–2009)
  • Monbiot, G. (2000), 'Captive State, The Corporate Takeover of Britain', Macmillan.
  • Venkat Raman, A. and JW Bjorkman (2009), 'Public-Private Partnerships in Health Care in India: Lessons for Developing Countries'. London. Routledge.
  • PwC Health Research Institute (2010), 'Build and beyond: The (r)evolution of healthcare PPPs' http://www.pwc.com/us/ppphealth
  • National Round Table on the Environment and the Economy (2012), 'Facing the elements: building business resilience in a changing climate' http://preventionweb.net/go/26487
  1. ^ Schaeffer, P.V. & S. Loveridge, 2002. “Toward an Understanding of Types of Public-Private Cooperation.” Public Performance and Management Review 26(2): 169-189.